Resource usage shows 200%, but actual hours only 10

E

Evan

Hey all,

I have a master schedule of about 5 sub schedules. When I open the master
and look on the resource usage view, I will see a resource who had worked 10
hours in one day on their tasks, but the resource usage view shows that the
resource unit % is 200%.

Now my understanding is that if the resource unit % is 200, that means the
resource worked 16 hours in that day.

Any help clearing up this issue would be greatly appreciated!
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top