S
Skip
I am new to Project, and am using 2003. Our construction company typically
runs 10 to 15 projects at a time, running +/- 6 months. This is probably
pretty basic, but I have been unable to figure it out on my own .... Should
we be developing individual "files" for each project, and somehow linking
them together, or should we run one "master" schedule, and either build the
unique schedules and/or import templates into the master schedule. ALSO ...
in my experimentation, I embedded a sample project into what I called a
master schedule, regretted it, and have been unable to remove the embedded
sample project. I select the "parent" task, press delete, it warns me that
I'm deleting a taks that has subs, but I click okay, but it doesn't delete???
What's going on here? Thanks in advance.
runs 10 to 15 projects at a time, running +/- 6 months. This is probably
pretty basic, but I have been unable to figure it out on my own .... Should
we be developing individual "files" for each project, and somehow linking
them together, or should we run one "master" schedule, and either build the
unique schedules and/or import templates into the master schedule. ALSO ...
in my experimentation, I embedded a sample project into what I called a
master schedule, regretted it, and have been unable to remove the embedded
sample project. I select the "parent" task, press delete, it warns me that
I'm deleting a taks that has subs, but I click okay, but it doesn't delete???
What's going on here? Thanks in advance.