Ms Project calculates all the ratios which are necessary to built the S
Curves. Look at the Earned Value table : you'll see the BCWS, BCWP, ACWP...
But MS Project Standard doesn't show the 3 curves in a a graph.
Nevertheless, it's possible to export the necessary data to Excel, and build
the graph in Excel : use the "Analyse Timescale Data into Excel" button
(Analysis tool bar)