I'm trying to make a schedule wherein there are tasks that recurring for
example:
Activity A: 7:00 am to 8:30 am every Monday and Wednesday for 5 months in
Room 101
Activity B: 8:30 am to 9:00 am every Monday and Wednesday for 4 months in
Room 101
Activity C: 7:00 am to 8:30 am every Monday and Wednesday for 4 months in
Room 102
etc.

Thanks! :)
 
S

Steve House [MVP]

Use the Recurring Task entry in the Insert menu.

Make sure the Project calendar has the workday day starting at 7am or
earlier. Enter TaskA as weekly on Mon & Wed, duration 30 min, starting on
the first Monday you want it to occur at 730am and continuing for however
many weeks you need it or to a cutoff date. Do the same for the other two
tasks with their own starting dates and times. The room is irrelevant to
Project.
 
J

JulieD

Hi

and further to Steve's excellent comments - you could put the room in as a
resource (and assign it to the tasks) to ensure that you haven't double
booked them.

Cheers
JulieD
 
I

Iconoclast

Hello
Is there any way to make MS Project detect the double booking?

Thank you.
 
J

JulieD

Hi

if you assign to meetings to the same resource, whether it be a room or a
person, then it will show in red in the resource sheet (known as
"overallocated") to see why a resource is overallocated you can use the
resource allocation view.

However, Project won't WARN you that you're trying to overallocate a
resource in the assignment stage.

Hope this helps
Cheers
JulieD
 