G
Genohem
Hi everyone, im in a very unusual situation. I have 4 projects and i need to
consolidated all of them. Im going to work in a main/master project. In this
project im gonna make all the changes that i need to adjust for my other
projects. I have a question.
In the master project i have a list of companies and the task that we are
following with them, and in my others projects i have a detailed information
of the list of companies mention in the master project. For example, in DECO
Company i have a numbers of task and subtask, and in my main project i have
DECO Company but only the percentage of cover task. I want to know if exists
the facillities to change the start date and end date in the main project and
in the same time in my others projects.
Note: in the individual projects i dont have a start/end dates field, i
assign it with the task information, it means, i put it manually.
consolidated all of them. Im going to work in a main/master project. In this
project im gonna make all the changes that i need to adjust for my other
projects. I have a question.
In the master project i have a list of companies and the task that we are
following with them, and in my others projects i have a detailed information
of the list of companies mention in the master project. For example, in DECO
Company i have a numbers of task and subtask, and in my main project i have
DECO Company but only the percentage of cover task. I want to know if exists
the facillities to change the start date and end date in the main project and
in the same time in my others projects.
Note: in the individual projects i dont have a start/end dates field, i
assign it with the task information, it means, i put it manually.