Hi,

I have set up the working time and calender for the teams working as in the
pattern below.


Monday Tuesday Wednesday Thursday Friday Saturday Sunday
Crew A D D C N N C C
Crew B C D D C N N C
Crew C C C D D C N N
Crew D N C C D D C N
Crew E N N C C D D C
Crew F C N N C C D D
Crew G D C N N C C D


Can some one help me on how I can do it in MS project

Thanks,
Krishna
 