D
Dan
I use a resource pool and link this to many projects.
However, what I would like to do is produce a report that shows what
projects each individual in my resource pool is working on - on a daily
basis. I don't want to go down to task or job level, just project. So, for
example, I have 3 projects on the go, P1, P2 and P3 and Dave is meant to be
working on P1 every day in june except for 4 days, where he will instead be
working on project P2. Steve on the other hand will be working on P1 for
week 1, P2 for week 2, P3 for week 3 and P4 for week 4.
I would like a report that shows something like:
June
01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22
.... 30
Dave P1 P2 P1 P1 P1 P1 P1 P1 P1 P2 P1 P1 P1 P1 P1 P2 P1 P1 P1 P1 P1 P2
.... etc
Steve P1 P1 P1 P1 P1 P1 P1 P2 P2 P2 P2 P2 P2 P2 P3 P2 P2 P2 P2 P2 P2 P3
.... etc
I'd be grateful if someone could point me in the right direction.
Kind regards,
Dan
However, what I would like to do is produce a report that shows what
projects each individual in my resource pool is working on - on a daily
basis. I don't want to go down to task or job level, just project. So, for
example, I have 3 projects on the go, P1, P2 and P3 and Dave is meant to be
working on P1 every day in june except for 4 days, where he will instead be
working on project P2. Steve on the other hand will be working on P1 for
week 1, P2 for week 2, P3 for week 3 and P4 for week 4.
I would like a report that shows something like:
June
01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22
.... 30
Dave P1 P2 P1 P1 P1 P1 P1 P1 P1 P2 P1 P1 P1 P1 P1 P2 P1 P1 P1 P1 P1 P2
.... etc
Steve P1 P1 P1 P1 P1 P1 P1 P2 P2 P2 P2 P2 P2 P2 P3 P2 P2 P2 P2 P2 P2 P3
.... etc
I'd be grateful if someone could point me in the right direction.
Kind regards,
Dan