P
ProjectNewbie
OK, so I have more information for a better formulated question....
Create a task in MS Project.
Duration = 3 Days
Work = 10 Hours
Now, let's enter some actual time to this task... how about 8 hours.
And now, let's change the duration from 3 days to 1 day.
Actual work changes?
And if I increase duration, actual work now moves with work and can actually
exceed the original 8 hours that was posted there.
Soooo, my questions is... if there is a calculation for actual work, what is
the formula and ultimately how do I make the above stop happening. I realize
this isn't a big deal for small tasks that span over a week or two, but
imagine this happening to tasks that span over months. A slight downward
change in duration could throw the whole plan off. Can anybody help me?
Create a task in MS Project.
Duration = 3 Days
Work = 10 Hours
Now, let's enter some actual time to this task... how about 8 hours.
And now, let's change the duration from 3 days to 1 day.
Actual work changes?
And if I increase duration, actual work now moves with work and can actually
exceed the original 8 hours that was posted there.
Soooo, my questions is... if there is a calculation for actual work, what is
the formula and ultimately how do I make the above stop happening. I realize
this isn't a big deal for small tasks that span over a week or two, but
imagine this happening to tasks that span over months. A slight downward
change in duration could throw the whole plan off. Can anybody help me?