space management

M

Maxime M.

Good day,

Can we have "Classrooms" considered resource. I want to
track which classrooms is used at any given time. We
teach Navigation, so at times studends are must be in
SIMULATOR 1 and at other times in SIMULATOR 2. Some
times, the must be in CLASSROOM A, and sometimes in the
CLASSROOM B or the AUDITORIUM or the GYM.

For every hour of use of the simulator, there is an
associated maintence cost.

How to keep track of this.

Thank you
 
G

Gérard Ducouret

Hello Maxime,
You can declare your classrooms and your simulators as resources in the
Resource Sheet.
On a task named "Lesson 3" for example, you can assign the Classroom 2
MS Project will tell you is the Classroom 2 is available during this period
of time.

Gérard Ducouret
 