Standard rate / per hour

J

Jackie

Hello

I would be grateful if you could let me know whether you can enter the
standard rate for project resources as a day rate and not per hour.

Many thanks
J
 
S

Syed Ali Abid

You can do it by going to Resource Sheet->Double click on a resource->Goto
Cost tab of Resource Information dialog->In cost rate table enter the cost
of the resource/day i.e. $ 10.00/d, by default it would be showing $0.00/h.

Abid
 
J

Jackie

thanks!

Syed Ali Abid said:
You can do it by going to Resource Sheet->Double click on a resource->Goto
Cost tab of Resource Information dialog->In cost rate table enter the cost
of the resource/day i.e. $ 10.00/d, by default it would be showing $0.00/h.

Abid
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top