I
ianogara
We have training programmes rolling out across several geographies say Task
A, Task B;
The Central team has to prepare the content say Task 1;
Clearly the prep has to be done ahead of any rollout (but particularly ahead
of the earliest rollout).
Hence should be logical that we use the Start-to-Finish (SF) function to
drive Task 1 i.e. Task 1 = Task A SF, Task B SF.
This also means that if Task B gets unexpectedly implemented ahead of Task A
then Task 1 adjusts accordingly.
However, when using SF, MS Project seems to schedule Task 1 to be only ahead
of the latest rollout.
How do I ensure Task 1 is always SF for the earliest of Task A, Task B etc?
Many thanks
Ian
A, Task B;
The Central team has to prepare the content say Task 1;
Clearly the prep has to be done ahead of any rollout (but particularly ahead
of the earliest rollout).
Hence should be logical that we use the Start-to-Finish (SF) function to
drive Task 1 i.e. Task 1 = Task A SF, Task B SF.
This also means that if Task B gets unexpectedly implemented ahead of Task A
then Task 1 adjusts accordingly.
However, when using SF, MS Project seems to schedule Task 1 to be only ahead
of the latest rollout.
How do I ensure Task 1 is always SF for the earliest of Task A, Task B etc?
Many thanks
Ian