Hi
I have a project where i have a colum with budget pr. task.
Ex.
Task Id 1 have budget $ 100 startdate 01.03.2006 enddate 04.03.2006
Task Id 2 have budget $ 200 startdate 15.03.2006 enddate 16.05.2006
Task Id 3 have budget $ 250 startdate 04.02.2006 enddage 05.02.2006
I need to have a report where i can see the budget pr. month.
Ex.
Februar 2006 Budget
Task Id 3 $250
Total $250
Marts 2006
Task id 1 $100
Task id 2 $200
Total $300
How do i do this ???
Thanks very much for your help
Br.
Jan
I have a project where i have a colum with budget pr. task.
Ex.
Task Id 1 have budget $ 100 startdate 01.03.2006 enddate 04.03.2006
Task Id 2 have budget $ 200 startdate 15.03.2006 enddate 16.05.2006
Task Id 3 have budget $ 250 startdate 04.02.2006 enddage 05.02.2006
I need to have a report where i can see the budget pr. month.
Ex.
Februar 2006 Budget
Task Id 3 $250
Total $250
Marts 2006
Task id 1 $100
Task id 2 $200
Total $300
How do i do this ???
Thanks very much for your help
Br.
Jan