A
Azhar
Hi,
Im currently building a project schedule and would like to know if its
possible to have sample dates in the schedule.
For Example I have a milestone saying contract signarute and all other
activites happen after it , but instead of putting in an actual date i Put in
DAY0 ot T0. And everythign else is mapped accordingly .
Start End Duration Predecessor
Contract Signature T0 T0 0
Order Equipment T0+1 T0+5 5days 1
so an
Im currently building a project schedule and would like to know if its
possible to have sample dates in the schedule.
For Example I have a milestone saying contract signarute and all other
activites happen after it , but instead of putting in an actual date i Put in
DAY0 ot T0. And everythign else is mapped accordingly .
Start End Duration Predecessor
Contract Signature T0 T0 0
Order Equipment T0+1 T0+5 5days 1
so an