T+1 Project Dates

A

Azhar

Hi,

Im currently building a project schedule and would like to know if its
possible to have sample dates in the schedule.

For Example I have a milestone saying contract signarute and all other
activites happen after it , but instead of putting in an actual date i Put in
DAY0 ot T0. And everythign else is mapped accordingly .

Start End Duration Predecessor
Contract Signature T0 T0 0
Order Equipment T0+1 T0+5 5days 1


so an
 
J

JulieS

Hello Azhar,

If you set the Project start date (Project > Project Information)
and create the predecessor relationships appropriately, you will get
what you need. If you need to shift the project, change the Project
start date. There is no Day0 to Project -- it will always be a
date/time. You can change the way the Gantt chart timescale shows
information through Format > Timescale, but the Start and Finish
dates will be actual dates.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 