Task 100% complete in Project Professional (PP) 2003 but 0% in PWA timesheet

E

ep

Hi,

Have updated an assignment to 100% complete in PP2003, however
remains at 0% in PWA timseheet, despite having gone via Collaborate/
Publish/New & Changed Assignments.
Would you know why?

Thanks.
 
S

Sean

Hi,

Have updated an assignment to 100% complete in PP2003, however
remains at 0% in PWA timseheet, despite having gone via Collaborate/
Publish/New & Changed Assignments.
Would you know why?

Thanks.

Check the setting in Tools-Options-Collaborate to have it set to have
updates to resources be "Any task information changes" not just Start,
Finish, % or Outline changes. If you only change remaining work, no
assignment change goes to PWA by default. The other item to do is a
Collaborate-Publish-Republish Assignments with Overwrite selected.
 
E

ep

Check the setting in Tools-Options-Collaborate to have it set to have
updates to resources be "Any task information changes" not just Start,
Finish, % or Outline changes. If you only change remaining work, no
assignment change goes to PWA by default. The other item to do is a
Collaborate-Publish-Republish Assignments with Overwrite selected.

Bingo! Thanks a lot.
 