J
johnm
My question centers arround the statement in the remark section of the "Help on % Work Complete" that I have included .
Remarks By default, changes to a task's percent work complete value affect the actual work value. Similarly, changes to the actual work value affect its percent work complete value. You can change this default, and have percent work complete and actual work independent of one another. On the Tools menu, click Options, and then click the Calculation tab. Clear the Updating task status updates resource status check box.
Whether I have the "calculation button" checked or unchecked, adding "Actual Work" changes the "% Work Complete", and adding to the "% Work Complete" adds to the "Actual Work" This is contrary to the statement in the remarks paragraph. Is Microsoft wrong? Thanks.
Remarks By default, changes to a task's percent work complete value affect the actual work value. Similarly, changes to the actual work value affect its percent work complete value. You can change this default, and have percent work complete and actual work independent of one another. On the Tools menu, click Options, and then click the Calculation tab. Clear the Updating task status updates resource status check box.
Whether I have the "calculation button" checked or unchecked, adding "Actual Work" changes the "% Work Complete", and adding to the "% Work Complete" adds to the "Actual Work" This is contrary to the statement in the remarks paragraph. Is Microsoft wrong? Thanks.