Maybe im in a stupid mode today but I see 70 hours in the sheet for Work. In
the database ( Access ) MSP_TASKS.TASK_WORK shows 4200000. The only
calculation that this relates to is 72 Hours = 4200 Minutes X 1000. This
calculcation works out for all fields. So my question is why is Project
doing this. Im sure there is some fuzzy logic but cant think of anything off
hand.