To simplify things, I have a project which covers two distinct phases. The
first or Research phase lasts several months. The second phase or
implementation phase spans two days and has numerous deadline times (eg.,
10:30 am, 2:15 pm, etc)within this two-day period. I'd like to represent the
time deadlines at their defined times and also the entire project from
research to implementation close. Can this be done in MS Project?
Thanks in advance.
Mike