Heres my situation. I have a large project with many dependencies set up.
Often times resources do not meet deadlines on their tasks and when I go in
to increase the duration, Id like to see all the successor tasks that are
impacted by this and what their "new" end dates would be if I did extend the
first task. Kinda like a "What If" scenario Ive seen in other PM softwares.
Im guessing this is a feature I just havent found yet. Please help.