new2msp --
Create your project with tasks, Durations, dependencies, constraints, notes,
etc. Add resources to the project using Tools - Build Team from Enterprise,
and then assign resources to each task as needed. Save your project to the
Project Server database. When you are ready to publish, click Collaborate -
Publish - All Information to "push" all of the project information to PWA.
If you make changes to the project, remember to save and publish the project
using Collaborate - Publish - All Information. When you receive task
updates from team members and process the updates into the project plan,
always remember to finish the update operation by clicking Collaborate -
Publish - All Information. Doing so will guarantee that your project
information in Microsoft Project and the project information in PWA are
synched up. Hope this helps.