T
Tat
I have seen that variance can be seen between a Baseline plan and the present
Interim plan(actual plan).
If i have modified my first baseplan 3 times,ie now i am having Baseplan
1,2,3 and an actual plan to track the progress.Then how can i view the
variance between Baseline1&actual plan,Baseline2&actual plan,Baseline3&actual
plan.
I have already checked with Multiple Gannt chart view.I want to see interms
of variance.Will it be possible?
Need ur help...Thanku.
Interim plan(actual plan).
If i have modified my first baseplan 3 times,ie now i am having Baseplan
1,2,3 and an actual plan to track the progress.Then how can i view the
variance between Baseline1&actual plan,Baseline2&actual plan,Baseline3&actual
plan.
I have already checked with Multiple Gannt chart view.I want to see interms
of variance.Will it be possible?
Need ur help...Thanku.