I have seen that variance can be seen between a Baseline plan and the present
Interim plan(actual plan).

If i have modified my first baseplan 3 times,ie now i am having Baseplan
1,2,3 and an actual plan to track the progress.Then how can i view the
variance between Baseline1&actual plan,Baseline2&actual plan,Baseline3&actual
plan.

I have already checked with Multiple Gannt chart view.I want to see interms
of variance.Will it be possible?

Need ur help...Thanku.
 
R

Rod Gill

Yes, but you need to add formulae to custom fields to calculate the
variance. For example set Number1=[Baseline1Start]-[Start]

--

Rod Gill
Project MVP

NEW!! Project VBA Book, for details visit: http://www.projectvbabook.com
 