View task cost by year for tasks that occur over multiple years

S

stinkrod35

There should be an easy way to view the estimated and actual cost of a
project that spans several years by year.

----------------
This post is a suggestion for Microsoft, and Microsoft responds to the
suggestions with the most votes. To vote for this suggestion, click the "I
Agree" button in the message pane. If you do not see the button, follow this
link to open the suggestion in the Microsoft Web-based Newsreader and then
click "I Agree" in the message pane.

http://www.microsoft.com/office/com...99e8-a106ad0c8ee5&dg=microsoft.public.project
 
J

John

stinkrod35 said:
There should be an easy way to view the estimated and actual cost of a
project that spans several years by year.

----------------
This post is a suggestion for Microsoft, and Microsoft responds to the
suggestions with the most votes. To vote for this suggestion, click the "I
Agree" button in the message pane. If you do not see the button, follow this
link to open the suggestion in the Microsoft Web-based Newsreader and then
click "I Agree" in the message pane.

http://www.microsoft.com/office/community/en-us/default.mspx?mid=58d30ef5-9463
-4fbe-99e8-a106ad0c8ee5&dg=microsoft.public.project

stinkrod35,
Your can. Just set the timescale for "years" in either the Task or
Resource Usage views.

John
Project MVP
 
J

Jan De Messemaeker

Fortunately, there is.
You couls have asked for it here.
Make the minor timescale years.
HTH
 