Want to show tasks ON project calender in Office 2004

B

Bunnyslippers

In the Project Center, I would like to be able to scan my weekly or
monthly Calendar and see all the project-related items (tasks (such as
deadlines), as well as events and appointments) that are occurring or
due on a given day. I don't want to have to look at separate windows
(e.g. Calendar AND Task windows) and I don't want to set up my Tasks as
Events. Since most of my tasks have due dates, is there a way to make
them show up on the Calendar? If not, there should be.
 
B

Bunnyslippers

After posting the above question (twice...sorry), I was knocking around
in the project center, when I suddenly realized my tasks WERE showing
up in the Calender. Then I clicked on the "Schedule" tab,
and--boom--they WEREN'T in the Calendar anymore. Then I realized that
scheduled tasks DO show up on the calendar--but only in the "Overview"
tab. When you go to the "Schedule" tab, they are no longer in the
Calender--only in the Task list. A bug? If not, it sure is an
oversight. Why would you want them Calendarized (sorry) in the Overview
but not in the Schedule view?
 
Top