Hello,
I've managed to create a WBS code in Project Profession and I've published
it to Server. However, I am not getting all of the WBS numbers in PWA. I
see only the minor tasks numbers. For example:
WBS (blank) TASK1
4.1.1 Task 1a minor
4.1.2 Task 1b minor
WBS (blank) TASK2
5.1.1 Task 2a minor
5.1.2 Task 2b minor
What have I done wrong? Or, what am I not ding. Could someone help me
please. I am using Project Professional 2003 and Project Server 2003.
Thanks in advance.
braktooth
I've managed to create a WBS code in Project Profession and I've published
it to Server. However, I am not getting all of the WBS numbers in PWA. I
see only the minor tasks numbers. For example:
WBS (blank) TASK1
4.1.1 Task 1a minor
4.1.2 Task 1b minor
WBS (blank) TASK2
5.1.1 Task 2a minor
5.1.2 Task 2b minor
What have I done wrong? Or, what am I not ding. Could someone help me
please. I am using Project Professional 2003 and Project Server 2003.
Thanks in advance.