Weird Problems with Simple Schedule Implementation

C

Coop

We thought a simple approach to initially implement would be best. We have
tasks, whose finish and start dates are strictly driven by asap dependencies
and durations (at least that is our intent). Where we have hard dates, we
implemented the deadline feature to handle so MSProject would not change the
way it calculates. We also had to add the resources we expected to be able
to access the MSProject version of the schedule (vs. web), so we handled that
by having one task at the end of the schedule with those folks identified in
'resource name' (not sure if this is contributing to a problem). The only
other field we leverage is 'enterprise text 1' to hold the role name of the
intented 'doer', but that should be okay I think. But we have the following
anomalies we cannot explain/fix. We feel as though they may be related and
may have something to do with high level settings that we have set
incorrectly based on our approach (not sure if this is at the enterprise
level or perhaps the review Calculation or Schedule tabs under
tools/options). Any help would be much appreciated. Problems are as follows:
-the status does not reflect properly i.e. Late, on Schedule, future, etc.
This is a real problem for us because we were hoping to use this field to
communicate Red, Yellow, Green to our execs.
-some durations we can change, some not...Wizard tells us we are creating a
schedule conflict - not sure why, as again, we only have asap constraints

Again, I am not clear that we have the proper 'switches' set based on the
simple approach we are taking (described above).

In the Schedule Options, we have
fixed units checked - doesnt seem like this should matter based on approach?
split in progress checked - seems like we want this
Tasks will honor constraints - seems like it wouldn't matter?
the two durations are estimates fields - not sure why that would be a problem?

In the Calculation Options, we have
Updating task status updates resource status checked - shouldn't matter?
Inserted projects calculated like summary checked - fine?
actual costs calculated by MSProj checked - shouldn't matter?

Hoping those out there with more experience than I might know of something
or point me somewhere.

I have been reading up on work and units (those terms come up alot)...seems
as though they are only important if you are using resources???
 
M

Mike Glen

Hi Coop,

Welcome to this Microsoft Project newsgroup :)

I hardly know whether to jump in here as you are obviously using or
intending to use Project Pro on a server, and I have no server or Project
pro:( However, I can, I hope help with some of the basics. My comments are
in line below. I then suggest you post on the server newsgroup. Please see
FAQ Item: 24. Project Newsgroups. FAQs, companion products and other
useful Project information can be seen at this web address:
http://www.mvps.org/project/.

Hope this helps - please let us know how you get on :))

Mike Glen
MS Project MVP
We thought a simple approach to initially implement would be best.
We have tasks, whose finish and start dates are strictly driven by
asap dependencies and durations (at least that is our intent).
------------------
Good - that's the way Project is designed to be used :)
=================
Where
we have hard dates, we implemented the deadline feature to handle so
MSProject would not change the way it calculates.
-------------
I hope the hard dates are the Deadline dates and you have retained the ASAP
Constraint rather than a Must Start/Finish on Constraint. If not, this
could cause problems with scheduelling.
================
We also had to add
the resources we expected to be able to access the MSProject version
of the schedule (vs. web), so we handled that by having one task at
the end of the schedule with those folks identified in 'resource
name' (not sure if this is contributing to a problem).
------------------
I would delete this task as it is not productive in achieving your
deliverables. Instead, just fill in Resource details in the Resource Sheet
view.
================
The only
other field we leverage is 'enterprise text 1' to hold the role name
of the intented 'doer', but that should be okay I think. But we have
the following anomalies we cannot explain/fix. We feel as though
they may be related and may have something to do with high level
settings that we have set incorrectly based on our approach (not sure
if this is at the enterprise level or perhaps the review Calculation
or Schedule tabs under tools/options). Any help would be much
appreciated. Problems are as follows: -the status does not reflect
properly i.e. Late, on Schedule, future, etc. This is a real problem
for us because we were hoping to use this field to communicate Red,
Yellow, Green to our execs.
--------------------
I don't really understand this as I presumed you were still in the planning
stage. You haven't assigned resources yet so no work can have been done, so
how can you expect to show status?
================
-some durations we can change, some
not...Wizard tells us we are creating a schedule conflict - not sure
why, as again, we only have asap constraints
-----------------
Possibly caused by Must... constraints: View/Table:Entry/More Tables... and
select the Constraint table to check all are ASAP . Can also be caused by
precedence links attached to Summary Tasks - try removing them.
===============
Again, I am not clear that we have the proper 'switches' set based on
the simple approach we are taking (described above).

In the Schedule Options, we have
fixed units checked - doesnt seem like this should matter based on
approach? split in progress checked - seems like we want this
Tasks will honor constraints - seems like it wouldn't matter?
the two durations are estimates fields - not sure why that would be a
problem?

In the Calculation Options, we have
Updating task status updates resource status checked - shouldn't
matter? Inserted projects calculated like summary checked - fine?
actual costs calculated by MSProj checked - shouldn't matter?
------------------
I don't think any of the above settings should cause you problems.
================
Hoping those out there with more experience than I might know of
something
or point me somewhere.

I have been reading up on work and units (those terms come up
alot)...seems as though they are only important if you are using
resources???
--------------------
You might like to have a look at my series on Microsoft Project in the
TechTrax ezine, particularly #5 and #10 , at this site:
http://tinyurl.com/2xbhc (Perhaps you'd care to rate it before leaving the
site, :) Thanks.)
=================
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top