I have a massive project plan, some 6000+ tasks, that is tracked weekly. Due
to the breadth of the plan, it spans several functional managers, who I have
given access to the project file for ease of updating.
Problem is that when I open the file, and notice a major milestone has
slipped, it is a painful and timely process to detetmine which tasks caused
the slip.
Despite the fact that I beleive that there should be only 1 person making
the updates, me, it seems if we try to get the functional managers together
for a single update, it takes forever and wastes other peoples time.
Is there an easy method to debug this situation? Traversing Preds is
painful, and often leads to several dead ends.
to the breadth of the plan, it spans several functional managers, who I have
given access to the project file for ease of updating.
Problem is that when I open the file, and notice a major milestone has
slipped, it is a painful and timely process to detetmine which tasks caused
the slip.
Despite the fact that I beleive that there should be only 1 person making
the updates, me, it seems if we try to get the functional managers together
for a single update, it takes forever and wastes other peoples time.
Is there an easy method to debug this situation? Traversing Preds is
painful, and often leads to several dead ends.