Is there any way to have the @workday function factor in
Holiday's as non-business day's?

Thanks,

Ben
 
J

JE McGimpsey

If you're talking about the WORKDAY() function (@ is a Lotus thing...),
then yes. See Help - it explains clearly the

=WORKDAY(start_date,days,holidays)

syntax. Note that holidays can be a list or a range.
 
B

Ben

Thanks for both tips!

Ben
-----Original Message-----
If you're talking about the WORKDAY() function (@ is a Lotus thing...),
then yes. See Help - it explains clearly the

=WORKDAY(start_date,days,holidays)

syntax. Note that holidays can be a list or a range.


.
 