David Ch
I have read several post regarding how to track a project againts the
original plan. I have found a way to show where the project progress should
be in a given date. On the TOOLS/TRACKING, you go to Update Project. Then a
window pop-up asking for some more detail. There is a field for date, set it
up and click go; the project will change its STATUS column to a % of progress
for the given date.
The issue is that if you save your file, you will lost the ACTUAL progress.
Now, how can I have this function to update a column and then look where we
should be on the project without lost the ACTUAL % progress.
I read the earned value advice but I still don't like it. I would like even
to plot my actual progress againts my plan, but so far, the ony way i found
to do this, is by manually getting data from microsoft project and then,
typing it on excel and plotting from there.
original plan. I have found a way to show where the project progress should
be in a given date. On the TOOLS/TRACKING, you go to Update Project. Then a
window pop-up asking for some more detail. There is a field for date, set it
up and click go; the project will change its STATUS column to a % of progress
for the given date.
The issue is that if you save your file, you will lost the ACTUAL progress.
Now, how can I have this function to update a column and then look where we
should be on the project without lost the ACTUAL % progress.
I read the earned value advice but I still don't like it. I would like even
to plot my actual progress againts my plan, but so far, the ony way i found
to do this, is by manually getting data from microsoft project and then,
typing it on excel and plotting from there.