Hi all,
I have one resource assigned to a task. The task duration is 8 hours and
the resource costs $12.50/hour with $12.50 for overtime. The Planned Cost is
therefore $100. After 8 hours of actual work being applied to this task we
see that we need to apply at least 16 more hours of work to complete the
task. When we complete 9 hours of work, we should have ACWP equal to $112.50,
but instead it is recorded as only $100. Also, the BCWP should be $100.
Instead, I have an ACWP equal to $100 and a BCWP equal to $0.00. Am I
missing something? Shouldn't these values be $112.50 and $100 respectively?
Thanks,
Glenn
I have one resource assigned to a task. The task duration is 8 hours and
the resource costs $12.50/hour with $12.50 for overtime. The Planned Cost is
therefore $100. After 8 hours of actual work being applied to this task we
see that we need to apply at least 16 more hours of work to complete the
task. When we complete 9 hours of work, we should have ACWP equal to $112.50,
but instead it is recorded as only $100. Also, the BCWP should be $100.
Instead, I have an ACWP equal to $100 and a BCWP equal to $0.00. Am I
missing something? Shouldn't these values be $112.50 and $100 respectively?
Thanks,
Glenn