I'm using '03 and have a PM overhead task spread over the duration of the
project. I enter the cost in the cost field. The matching PM resource is work
and no std rate. When the task is 'update as scheduled' (fixed units/effort
driven off), ACWP updates correctly, but no BCWS/BCWP entries.
I have resources with std. rate entries and assignments to tasks. When they
are updated (either actual duration or actual work) no entries are made in
the earned value BCWS/BCWP/CV.
Any clue as to what I am doing wong?
Thanks
I'm using '03 and have a PM overhead task spread over the duration of the
project. I enter the cost in the cost field. The matching PM resource is work
and no std rate. When the task is 'update as scheduled' (fixed units/effort
driven off), ACWP updates correctly, but no BCWS/BCWP entries.
I have resources with std. rate entries and assignments to tasks. When they
are updated (either actual duration or actual work) no entries are made in
the earned value BCWS/BCWP/CV.
Any clue as to what I am doing wong?
Thanks