W
Wireman
hi buddies,
I have set the physical % complete for earned value calculation in my MS
Project 2003. I found something confused for the BCWP calculation.
The calulation of ACWP is correct for the tasks which's finish later than
current date as below.(BCWP = Baselined Cost * Physical % Complete, it's
correct!)
% Complete || Physical % Complete || Finish || Current Date ||
Baslined Cost|| Actual Cost || BCWS || BCWP || ACWP
25% || 20% || 03/28/2008|| 03/21/2008
|| 80 || 20 || 40 || 16 || 20
However, if the task is delayed which means the finish date is before
current date. The BCWP is totally different.
% Complete || Physical % Complete || Finish || Current Date ||
Baslined Cost|| Actual Cost || BCWS || BCWP || ACWP
25% || 20% || 03/14/2008|| 03/21/2008
|| 80 || 20 || 80 || 20 || 20
It seems MS Project still use % Complete to calcualte the BCWP for the
delayed tasks, even the setting for cauculation is Physical % Complete
already.
How could I always get the BCWP = Baselined Cost * Physical % Complete, no
matter the task is delayed or not? Anyone can help me? Thanks in advance.
I have set the physical % complete for earned value calculation in my MS
Project 2003. I found something confused for the BCWP calculation.
The calulation of ACWP is correct for the tasks which's finish later than
current date as below.(BCWP = Baselined Cost * Physical % Complete, it's
correct!)
% Complete || Physical % Complete || Finish || Current Date ||
Baslined Cost|| Actual Cost || BCWS || BCWP || ACWP
25% || 20% || 03/28/2008|| 03/21/2008
|| 80 || 20 || 40 || 16 || 20
However, if the task is delayed which means the finish date is before
current date. The BCWP is totally different.
% Complete || Physical % Complete || Finish || Current Date ||
Baslined Cost|| Actual Cost || BCWS || BCWP || ACWP
25% || 20% || 03/14/2008|| 03/21/2008
|| 80 || 20 || 80 || 20 || 20
It seems MS Project still use % Complete to calcualte the BCWP for the
delayed tasks, even the setting for cauculation is Physical % Complete
already.
How could I always get the BCWP = Baselined Cost * Physical % Complete, no
matter the task is delayed or not? Anyone can help me? Thanks in advance.