J
Jeff Hackett
BCWS appears to be updating correctly as STATUS date is updated but BCWP is
never greater than BCWS and therefore SPI is never greater than 1.0 (i.e.
Project is taking no credit for work completed ahead of schedule). This is
true for a single task (e.g. current date is exactly halfway through $100
task, BCWS = $50, if % Complete is set to 25%, I get BCWP = $25, if I set %
Complete to 50%, I get BCWP = $50, if I set % Complete to 100%, BCWP stays at
$50.). It's also true if I take % Complete credit on a Task that starts on a
date after the Project Status date.
never greater than BCWS and therefore SPI is never greater than 1.0 (i.e.
Project is taking no credit for work completed ahead of schedule). This is
true for a single task (e.g. current date is exactly halfway through $100
task, BCWS = $50, if % Complete is set to 25%, I get BCWP = $25, if I set %
Complete to 50%, I get BCWP = $50, if I set % Complete to 100%, BCWP stays at
$50.). It's also true if I take % Complete credit on a Task that starts on a
date after the Project Status date.