Inconsistant Earned Value Calculations

K

Karl

I am using fixed duration, not effort driven task type and physical %
complete.
BCWS for a task does not always match the sum of the BCWS for the
resources
BCWP for a task does not always match the sum of the BCWS for the
resources

Does anybody have any knowledge on this?

Karl
 
A

Andrew Lavinsky

This could happen if the baseline was changed. When you set a full baseline,
then set a partial baseline as part of a change management methodology, the
task/resource BCWS can get out of sync.

-A
 