D
DK
Hi,
I’m trying to get a handle on measuring EV performance using MS Project and
noticed there are six field categories for BCWS, BCWP & ACWP.
When I update my schedules I expect to see a combination of baseline and
status date updating the BCWS, actual duration plus remaining duration
updating the BCWP and actual work plus remaining work updating the ACWP.
Putting to one side the timephased fields... unless Microsoft are referring
to different views (Gantt, Resource, Task etc.), I’m actually at a loss to
see what the differences are between the BCWS, BCWP & ACWP task / resource /
assignments fields.
In layman’s terms could someone explain to me any of the distinctive
characteristics are and perhaps give some examples? Am I updating my
schedules using task, resource or assignment fields or by a combination? Will
BCWS, BCWP & ACWP show different values for each field category?
I’m using standalone 2k3
DK
I’m trying to get a handle on measuring EV performance using MS Project and
noticed there are six field categories for BCWS, BCWP & ACWP.
When I update my schedules I expect to see a combination of baseline and
status date updating the BCWS, actual duration plus remaining duration
updating the BCWP and actual work plus remaining work updating the ACWP.
Putting to one side the timephased fields... unless Microsoft are referring
to different views (Gantt, Resource, Task etc.), I’m actually at a loss to
see what the differences are between the BCWS, BCWP & ACWP task / resource /
assignments fields.
In layman’s terms could someone explain to me any of the distinctive
characteristics are and perhaps give some examples? Am I updating my
schedules using task, resource or assignment fields or by a combination? Will
BCWS, BCWP & ACWP show different values for each field category?
I’m using standalone 2k3
DK