A
Agneta
Having some problem with the report. When I look at the ACWP, BCWP and BCWS
in for example the TaskUsage view I get correct information. When I then
create the report the AC is correct, the Planned Value (which I thought would
be BCWS) is correct for most weeks... But Earned Value (which I thought
should be BCWP) is not showing the TimePhased values. I´m using % Physical
Complete as Earned Value method. Someone please help!
in for example the TaskUsage view I get correct information. When I then
create the report the AC is correct, the Planned Value (which I thought would
be BCWS) is correct for most weeks... But Earned Value (which I thought
should be BCWP) is not showing the TimePhased values. I´m using % Physical
Complete as Earned Value method. Someone please help!