S
swell estimator
up until today all the schedules I've done use tasks only. I want to start
using resources. I've been reading the online help on this subject and I
find it confusing.
Can you talk me through a simple way to get started with resources?
Here's what I have in mind. One task in the project is carpentry, 40 days
duration. I want to assign a foreman, carpenter and laborer to this task. I
also want to notify these 3 workers ahead of time that they need to be on
this project on a certain date and I want the schedule to prompt the project
manager when he should give these workers this information.
using resources. I've been reading the online help on this subject and I
find it confusing.
Can you talk me through a simple way to get started with resources?
Here's what I have in mind. One task in the project is carpentry, 40 days
duration. I want to assign a foreman, carpenter and laborer to this task. I
also want to notify these 3 workers ahead of time that they need to be on
this project on a certain date and I want the schedule to prompt the project
manager when he should give these workers this information.