D
Duane Nutley
Whenever I have used the Analyze Timescaled Data I have never had a problem
with it. But recently someone asked why the wizard does not seem to work with
either the Cumulative % Complete or Percentage Complete fields.
So I went to an old project, put in actual values and ran the wizard. Stated
that I wanted the Percentage Complete field, not the Work field, told it for
the entire project and told it to graph.
The result - the graph is on 0% and in the sheet with the data, the Total
Percentage Complete contains 0.
Now when I did the same report but with the Work field it worked and I
noticed in the Total field that it uses the Sumif calculation, yet when I
used the Percentage Complete field it used no calculation and just had 0%.
Anyone else experienced the same problem, or if you try it what happens for
you?
Note I am using Project 2003 SP 3, and have tried it on Project 2003 SP 2. I
don't know which version of Project 2003 the original person had.
with it. But recently someone asked why the wizard does not seem to work with
either the Cumulative % Complete or Percentage Complete fields.
So I went to an old project, put in actual values and ran the wizard. Stated
that I wanted the Percentage Complete field, not the Work field, told it for
the entire project and told it to graph.
The result - the graph is on 0% and in the sheet with the data, the Total
Percentage Complete contains 0.
Now when I did the same report but with the Work field it worked and I
noticed in the Total field that it uses the Sumif calculation, yet when I
used the Percentage Complete field it used no calculation and just had 0%.
Anyone else experienced the same problem, or if you try it what happens for
you?
Note I am using Project 2003 SP 3, and have tried it on Project 2003 SP 2. I
don't know which version of Project 2003 the original person had.