Hi
I wanted to play around with the analyze timescaled data export
mechanism.
So I pressed it, selected entire project, kept the only entry "work",
entered the date (which basicall confuses the language and format
settings
of project, but who cares), chose no graph, and said export data.
I expected to see some resource names, then work they do and then
the days they work on this.
but the excel does not show any resource, although they are assigned
tot he tasks..
What do I do wrong?
Kay
I wanted to play around with the analyze timescaled data export
mechanism.
So I pressed it, selected entire project, kept the only entry "work",
entered the date (which basicall confuses the language and format
settings
of project, but who cares), chose no graph, and said export data.
I expected to see some resource names, then work they do and then
the days they work on this.
but the excel does not show any resource, although they are assigned
tot he tasks..
What do I do wrong?