K
KingKikapu
Is there a way to assign more than one of the same Material Resource t
a given task? I ask because if I attempt to assign another version o
the same resource to a task like the situation below...
_TASK_#1
Resource NameUnits (
Unit=1$)Cost
Material Resourc
A100,000.00$100,000.00
Material Resourc
A4,000.00$4,000.00
...then Project will REMOVE the first version of the resource and onl
keep the latter version of the resource. It will not add the tw
together before removing the first version; it will simply wipe th
first version out.
Can I then A) somehow assign two copies of a material resource wit
their independent totals, or B) Assign two copies of a material resourc
and somehow have Project combine (not replace) the two into one entry
a given task? I ask because if I attempt to assign another version o
the same resource to a task like the situation below...
_TASK_#1
Resource NameUnits (
Unit=1$)Cost
Material Resourc
A100,000.00$100,000.00
Material Resourc
A4,000.00$4,000.00
...then Project will REMOVE the first version of the resource and onl
keep the latter version of the resource. It will not add the tw
together before removing the first version; it will simply wipe th
first version out.
Can I then A) somehow assign two copies of a material resource wit
their independent totals, or B) Assign two copies of a material resourc
and somehow have Project combine (not replace) the two into one entry