P
Peters
I am doing the first baseline change in a project and I am facing some
challenges.
I have a baseline set. Lets say I should build a wall with 100 bricks in 10
days. My cost for this project is $1000.
Timewise and counting the number of bricks, I am halfway through the project
when my customer tells me he wants another 20 bricks. The problem is, my
project has spent more resources than expected, so even though I am halfway,
the cost is 60% of the total.
My problem is that when I add the necessary work to the work field needed to
complete the project with the new specification and set a new baseline, my
own cost overrun will be included in the baseline making the project looking
less overrun than it is.
If this was a larger project, with 100+ tasks, I would also like to be able
to point out maybe the 10 or 15 activities that was affected by the scope
change and to what degree, perhaps with information on baselin cost, duration
and start/finish.
I have tried to figure out some steps to go through using formulas and
filters to get everything to show, but have not succeded. Does anyone have
some good steps to follow to achive this?
Thanks in advance,
Peter
challenges.
I have a baseline set. Lets say I should build a wall with 100 bricks in 10
days. My cost for this project is $1000.
Timewise and counting the number of bricks, I am halfway through the project
when my customer tells me he wants another 20 bricks. The problem is, my
project has spent more resources than expected, so even though I am halfway,
the cost is 60% of the total.
My problem is that when I add the necessary work to the work field needed to
complete the project with the new specification and set a new baseline, my
own cost overrun will be included in the baseline making the project looking
less overrun than it is.
If this was a larger project, with 100+ tasks, I would also like to be able
to point out maybe the 10 or 15 activities that was affected by the scope
change and to what degree, perhaps with information on baselin cost, duration
and start/finish.
I have tried to figure out some steps to go through using formulas and
filters to get everything to show, but have not succeded. Does anyone have
some good steps to follow to achive this?
Thanks in advance,
Peter