V
Vic
Hi,
I inherited a project plan that uses the Baseline Cost and BCWS to calculate
a % to Plan field. And we've added many tasks. So I tried to re-baseline
the entire project but the Baseline Cost doesn't seem to want to
re-calculate. Am I doing something wrong?
I inherited a project plan that uses the Baseline Cost and BCWS to calculate
a % to Plan field. And we've added many tasks. So I tried to re-baseline
the entire project but the Baseline Cost doesn't seem to want to
re-calculate. Am I doing something wrong?