C
Craig L M
I am having a problem with the rollup to summary levels when I do a Baseline
Save for a single task.
If the earliest baseline start for all subtasks falls on a Friday, the
baseline cost for that first friday only doesn't roll up to the summary
level. All other days do. Basseline Work does. Is this a bug I found? (I
am using Project Pro 2003.) Can anyone reproduce this problem? Is there
some other reason Baseline Cost would not be rolling up for the first day if
it is Friday? (In my case May 18th 2007) If I move the baseline start for
one of the subtasks to 5/17/07, a Thursday, it rolls up correctly.
Save for a single task.
If the earliest baseline start for all subtasks falls on a Friday, the
baseline cost for that first friday only doesn't roll up to the summary
level. All other days do. Basseline Work does. Is this a bug I found? (I
am using Project Pro 2003.) Can anyone reproduce this problem? Is there
some other reason Baseline Cost would not be rolling up for the first day if
it is Friday? (In my case May 18th 2007) If I move the baseline start for
one of the subtasks to 5/17/07, a Thursday, it rolls up correctly.