In Project 2007, I have created a new .mpp file. I add several
tasks and
assign logic and durations to them. I create a baseline from
the
current
start and finish dates for each task using the Tools, Tracking,
Set Baseline
command. I add baseline start and finish as columns in my
view.
Then create
a custom text fields for responsibility. I then assign values
to
each task
for both custom field. For instance, I assign Bill to 5 tasks,
Mary to 5
tasks, and so on for responisbility. Then go to Project, Group
By, More
Groups and create a new grouping with the group by criteria as
the
responsibility custom text field. Look at the dates in the
grouping band for
baseline start. They are incorrect. It should show the
earliest
baseline
start for any task in the group. It is showing the baseline
start
for the
task in which the baseline finish is used in the group by band.
--
crpmst
:
Hello crpmst,
I'm sorry, I can't attempt to test your scenario with the
limited
information you've provided. Can you please be more specific?
What
values do you have in the custom fields? Specifically what is
your
Group definition?
Give us some more info and we'll try to assist.
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit
http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
I am using Project 2007 with SP2. When I use the Project,
Group
By
option
and use any custom field, the dates that are displayed in
the
Gantt table in
the Baseline Start field at the summary level are incorrect.
It
seems to be
displaying the baseline start of the task it is using to
determine
the
baseline finish for the summary. How can I get Project to
display
the
correct summary baseline start date?