BaseLine

S

Sam

I need to ask about baselines whether in project professional 2003 or project
professional 2007.

just suppose i have a one project in which i saved three baselines of
different dates.

1st jan, 2nd jan , 3rd jan

but after few days i want to open view--->table --> variance .

in this view from which date of baseline show values . and how i can select
different baselines to see in variance view.

may be i want to see a variance view with 2 jan . and may be a 3rd jan .

pls reply me soon.
 
G

Gérard Ducouret

Sam,



You will have to create some custom fields (maybe gathered together in
custom tables) with simple formulas such as :
[Baseline1 Finish]-[Finish]

Gérard Ducouret
 