A
Amy
I am hoping someone has an easier way to approach this process than I am
currently using.
The scenario: We us project 2007 to track consulting projects. At the
beginning of the project we set a baseline for the work and cost budget and
then enter actual work for each task as the project progresses. We
continually monitor our work variance and cost variance to the baseline.
When we have a change order that increases the budget I manually update the
baseline work and baseline cost to reflect the increase budget in the change
order. This can be a bit of work as the changes don’t automatically roll-up
to the summary tasks but it does give the information we need for updated
variance.
I have tried saving an updated baseline but the other iterations of the
baseline (‘baseline 1’) are not linked to any variance calculations. If I
save over the original baseline, for any tasks that are over budget (actual
work > baseline work and work) then the baseline will not equal the budget
amount.
Any suggestions?
Thanks
AC
currently using.
The scenario: We us project 2007 to track consulting projects. At the
beginning of the project we set a baseline for the work and cost budget and
then enter actual work for each task as the project progresses. We
continually monitor our work variance and cost variance to the baseline.
When we have a change order that increases the budget I manually update the
baseline work and baseline cost to reflect the increase budget in the change
order. This can be a bit of work as the changes don’t automatically roll-up
to the summary tasks but it does give the information we need for updated
variance.
I have tried saving an updated baseline but the other iterations of the
baseline (‘baseline 1’) are not linked to any variance calculations. If I
save over the original baseline, for any tasks that are over budget (actual
work > baseline work and work) then the baseline will not equal the budget
amount.
Any suggestions?
Thanks
AC