N
Nico
Hi,
I am trying to make MS Project to automatically increase the duration of the
project when manually changing the work time in a particular day on the
project, for a resource.
For example, let's say that a resource must work on a project for 3 hours a
day and as such the project completes in one week. What I want is to mark
that in a day the resource dis not work on that project (by entering 0h as
time allocated for the project for the day), and MS Project to see that and
automatically increase the duration of the project with one extra day,
because the work allocated for the project is fixed. At the end I want to see
that in the middle of the project the resource did not work for a day on it,
and as such the overall duration of the project has been increased.
I have not been able to do that from resource usage view. Is there a way to
do this ?
Thanks
I am trying to make MS Project to automatically increase the duration of the
project when manually changing the work time in a particular day on the
project, for a resource.
For example, let's say that a resource must work on a project for 3 hours a
day and as such the project completes in one week. What I want is to mark
that in a day the resource dis not work on that project (by entering 0h as
time allocated for the project for the day), and MS Project to see that and
automatically increase the duration of the project with one extra day,
because the work allocated for the project is fixed. At the end I want to see
that in the middle of the project the resource did not work for a day on it,
and as such the overall duration of the project has been increased.
I have not been able to do that from resource usage view. Is there a way to
do this ?
Thanks