P
Prasanna Adavi
I am not sure how to explain the following MS Project Behavior to one of My
project Managers.
We us MSP 2007 in a Project Server Environment, with SP2, and December Cum
Updates applied.
We have a schedule with tasks, type Fixed Duration. Some of the tasks have
multiple resources assigned to them, with equal work.
We have observed the following behaviour under task usage view.
Task Work Dur %work %comp remaining work
Task ABCD 12 hrs 4 hrs 67% 0% 4 hrs
Resource 1 4 hrs 100% 0 hrs
Resource 2 4 hrs 0% 4 hrs
Resource 3 4 hrs 100% 0 hrs
Theoretically, the % complete has to show some value if not exactly equal to
% work complete.
I think the problem is related to http://support.microsoft.com/kb/170704
Can somebody help me explain this?
project Managers.
We us MSP 2007 in a Project Server Environment, with SP2, and December Cum
Updates applied.
We have a schedule with tasks, type Fixed Duration. Some of the tasks have
multiple resources assigned to them, with equal work.
We have observed the following behaviour under task usage view.
Task Work Dur %work %comp remaining work
Task ABCD 12 hrs 4 hrs 67% 0% 4 hrs
Resource 1 4 hrs 100% 0 hrs
Resource 2 4 hrs 0% 4 hrs
Resource 3 4 hrs 100% 0 hrs
Theoretically, the % complete has to show some value if not exactly equal to
% work complete.
I think the problem is related to http://support.microsoft.com/kb/170704
Can somebody help me explain this?