I use MSP 2003 standalone. I have created a master plan with 4 inserted
plans, each having been baselined before I inserted. After inserting the
baselined plans, I then baselined the master plan. The BCWS, BCWP, and ACWP
all display $0.00 at the program (master) level, yet the inserted plans all
display values in those fields.
1. Why is this happening and will I have to re-baseline the master everytime
there is a change in one or more of the inserted plans?
2. What is the sequence in which I must insert and baseline plans to have
the master plan calculate EV correctly?
plans, each having been baselined before I inserted. After inserting the
baselined plans, I then baselined the master plan. The BCWS, BCWP, and ACWP
all display $0.00 at the program (master) level, yet the inserted plans all
display values in those fields.
1. Why is this happening and will I have to re-baseline the master everytime
there is a change in one or more of the inserted plans?
2. What is the sequence in which I must insert and baseline plans to have
the master plan calculate EV correctly?