J
Joey123
Hello everyone,
My problem today is in the Gannt Chart Timeline. What I'm having happe
is that I set up my gannt chart with predecessors and successor
manually and I have the arrows connecting each one. Now I'm wanting t
completely redo my time line and dates but I can't seem to get my date
for each task to go away.
Things I have tried...
Deleting the dates.
Deleting the bars on the graph
Redoing the dates with predecessors and successors to no avail.
Anyways I would really like to keep my Task Names, Durations, an
Resource Names the same while resetting the dates so I can completel
redo them.
thanks for the suggestions
Joe
My problem today is in the Gannt Chart Timeline. What I'm having happe
is that I set up my gannt chart with predecessors and successor
manually and I have the arrows connecting each one. Now I'm wanting t
completely redo my time line and dates but I can't seem to get my date
for each task to go away.
Things I have tried...
Deleting the dates.
Deleting the bars on the graph
Redoing the dates with predecessors and successors to no avail.
Anyways I would really like to keep my Task Names, Durations, an
Resource Names the same while resetting the dates so I can completel
redo them.
thanks for the suggestions
Joe