B
Bazzrington
Pulliing my hair out over this one. I have a 700+ line schedule and somehow
I've not only managed to loose the full critical path but more annoyingly the
gannt bars now show durations a day shorted than they are entered - the
actual start/finish dates are okay (as are depenedncies bewteen tasks). I.e.
a one day task has a barely perceptiple duration in the gantt dar and a two
day tasks shows a 1 day duration. Where there is a depenency, the dependency
is illustrated as if there it is fs+1d. I have zoomed right in to show only
days and reset the gantt wizard I don't know how many times. Any more
suggestions on whats up?
I've not only managed to loose the full critical path but more annoyingly the
gannt bars now show durations a day shorted than they are entered - the
actual start/finish dates are okay (as are depenedncies bewteen tasks). I.e.
a one day task has a barely perceptiple duration in the gantt dar and a two
day tasks shows a 1 day duration. Where there is a depenency, the dependency
is illustrated as if there it is fs+1d. I have zoomed right in to show only
days and reset the gantt wizard I don't know how many times. Any more
suggestions on whats up?