S
StarbucK
Hello I have an issue I hope can be resolved.
I am using MS project to create a Gantt chart to print.
The Durations is a measurement of weeks.
If a task takes 3 weeks in duration it will not show fully three weeks on
the graph, I'm pretty sure it wont finish a task on a Weekend for some
reason. Yet the next subsequent task starts on the Monday like it should.
Can anyone offer an explanation?
I am using MS project to create a Gantt chart to print.
The Durations is a measurement of weeks.
If a task takes 3 weeks in duration it will not show fully three weeks on
the graph, I'm pretty sure it wont finish a task on a Weekend for some
reason. Yet the next subsequent task starts on the Monday like it should.
Can anyone offer an explanation?